Presto Geosystems Menu
Google Translate

Dam Structure Safety Installation and Repair Using Advanced Geosynthetic Technology

Written By: Samantha Justice, P.E.

scenic view of damDams and Spillways Are a Critical Part of U.S. Infrastructure

With estimates of 84,000 structures nationwide, dams and spillways are essential for controlling flooding, water distribution and management, and providing hydroelectric power. Unfortunately, these structures cannot last forever. The average age of dams and spillways in the US is 57 years, seven years over the typical 50-year lifespan of these structures. Aging infrastructure can lead to serious consequences if safety precautions are not taken, or measures are not implemented to address identified problems in a timely manner. The most important measure that any dam manager can apply is continual inspection and upkeep.

The US Army Corps of Engineers Infrastructure Report Card rating for 2021 was a C-, and the health of dam structures was a significant part of that low rating. State and federal regulations provide a framework for the assessment and maintenance of dam and spillway structures-at a minimum yearly audit inspections that identify areas that need repair or replacement are required. Performing these repairs can help extend the lifetime of dams to help keep essential services in place without excessive cost or increased failure potential.

Understanding Areas of Concern for Existing Structures

The vast majority of America’s rivers and lakes have existing dams and spillways, and as such, very few new structures are being built. With new construction, safety measures can be incorporated during the design phase to extend the lifetime of the project and help prevent failures. The true threat is with existing structures that have gone past their intended lifetimes or have seen areas of potential failure.

A recent example of the potential for catastrophic damage due to a dam failure is the 2017 Oroville Dam crisis in Northern California. Extremely heavy rainfall over a number of days raised the level of Lake Oroville, increasing the flow over the main spillway to above-average levels.  Almost immediately, damage was observed in the lower half of the spillway, with a large section of the concrete path collapsing. The emergency spillway was utilized to help prevent further damage to the main spillway, however, excessive erosion occurred to the emergency spillway path, and emergency repairs were subsequently required to address damage in both spillway areas. Further damage occurred when more rainfall increased the lake level yet again, including blocking the downstream river and requiring the immediate shutdown of the Oroville hydroelectric power plant. Luckily, total collapse of the dam did not occur, but more than 180,000 residents of the Feather River Basin were required to evacuate for multiple days, and over the next year, more than 1,000 people worked more than 2 million hours to rebuild the spillways to ensure the safety of downstream communities.

With the passage of the 2021 Infrastructure Investment and Jobs Act, states will have access to funds to complete repairs and upgrades of aging dams and spillways before failure can occur. The failure at the Oroville Dam was preceded by rejection of a 2005 upgrade proposal to build a concrete emergency spillway that could have handled the high water flows seen in the 2017 event. Re-evaluating existing structures to ensure that they are still able to withstand 100-year and 500-year flood events is crucial to the longevity of the dam network within the US. Maintaining both upstream and downstream dam faces and spillways is an ongoing process, fighting against wave action and erosion, as well as any potential impact damage caused during storm events. Even simple maintenance of roads and work pads over dams can have a lasting effect on the health of these structures by allowing workers access to inspect and repair the structures quickly and easily.

GEOWEB® Geocells Are a Repair Solution for Dams and Spillway Sites

GEOWEB geocell technology is a versatile geosynthetic system that can be used to create long-term solutions for many of the common dam and spillway problem areas. Geocells function as the support structure for unpaved roadways, capable of supporting maintenance and repair vehicles. They also function as surface erosion control solutions, preventing the formation of rills or the collapse of unstable soils due to water flow, wave action, and storm events.

charleroi dam geocells

#image_titl

 

GEOWEB geocells can be placed on the upstream face of a dam structure to mitigate the effects of wave action on the dam, supporting existing riprap areas, or replacing them entirely with vegetation, gravel or concrete. The flexibility of the GEOWEB system allows for the use of mixed infill materials, such as topsoil above normal water levels for grass growth and small aggregate below the water level for erosion prevention. Comprised of high-density polyethylene (HDPE), GEOWEB geocells are formulated for long term durability to resist weathering, chemical attack, and ultraviolet radiation, and are therefore suitable for use in applications where the material will be subjected to cyclic wetting and drying, permanently submerged, or full sun exposure. The material is not prone to degradation or corrosion due to environmental factors, and can be placed on the downstream face of, or within, a spillway structure. The system is also compatible with concrete infill to accommodate extremely high flow velocities. For comparison, Table 1 summarizes allowable velocities and shear stresses for various channel lining alternatives.

 Comparison of allowable velocity and shear stress for channel lining alternatives

In emergency spillway areas, topsoil infill with vegetation can be used to allow for a natural camouflaged look, while still preventing erosion and uncontrolled water flow, and outperforming traditional unreinforced channel lining alternatives.

Staging areas and maintenance roads are also integral parts of a dam site, and when necessary, these features provide vital access and adequate ground support for vehicles and heavy equipment to perform inspections, routine maintenance, and repairs. The GEOWEB system can be used in a variety of load support applications, including unpaved access roads, laydown areas, and parking lots. Reinforcing these roads means significantly reduced maintenance requirements, reduced rutting, and access to areas that might otherwise be unable to support heavy loads due to soft soil conditions. Minimizing stresses on top of dam structures is critically important to preventing the formation of cracks or slumps within the structure that could lead to failure. The GEOWEB road system can be integrated with the slope protection system on the upstream and downstream faces of the dam for a continuously protected berm from water, vehicle, and impact loads.

mud lake dam geocells

Design Support & Resources for the GEOWEB System Applications

The engineering team at Presto Geosystems works closely with engineers and project planners, offering free project evaluation services and on-site support. Our recommendations will deliver a technically sound, cost-effective solution based on four decades of accredited research and testing data. Please contact our knowledgeable staff and network of qualified distributors and representatives to discuss your project needs today.

Related Articles and Case Studies

Mud Lake Dam Rehabilitation
Olivenhain Dam Power Line Access

References

United States Department of Agriculture, Natural Resources Conservation Service, (2007) Part 654 Stream Restoration Design, National Engineering Handbook, Chapter 8, Threshold Channel Design, (viewed 23 March 2022 and available https://directives.sc.egov.usda.gov/OpenNonWebContent.aspx?content=17784.wba as a link directly to Chapter 8). Table 8-11 “Allowable velocity and shear stress for selected lining materials” referenced from 8-37.

Colorado State University, Engineering Research Center (2009) Hydraulic Testing and Data Report for GEOWEB 30v with Concrete, research summary courtesy Presto Geosystems, (viewed 23 March 2022 and available Colorado State University Testing PDF)

Sustainable Vegetated Channels = The Death of Rip Rap

Rip rap is a common channel protection method because of its resistance to most flows with appropriate rock size; however, it does have significant drawbacks. Material can be expensive, not locally available, and placement requires heavy equipment. Additionally, rip rap channels are prone to regular maintenance, collection of debris and garbage, erosion at boundaries, undermining, and movement.

Naturally vegetated channels are grassed greenways that offer substantially lower maintenance and cost but are limited in their ability to resist moderate-high flows and shear forces even for short durations—unless the soils and vegetation can be stabilized.

High-Performing Vegetated Solution

The GEOWEB® Soil Confinement System offers protection to channels with continuous low flows—as well as moderate-to-high flow intermittent channels. The system’s honeycomb-like network creates check-dams that protect the soil layer from hydrological erosive forces and resulting erosion that impacts unconfined soils. Cell wall perforations lock up with the vegetative root for further stabilization.

The GEOWEB single-layer vegetated channels can withstand ~9 ft/s (2.7 m/s), more than doubling the resistance of typical unsupported vegetated channels (4 ft/s (1.2 m/s). The GEOWEB channels can withstand even higher velocities—as high as 30 ft/s (9m/s)—with an overlying Turf Reinforcement Mat (TRM) when fully vegetated. This is a significant improvement, essentially doubling performance resistance to shear stress and velocities for TRMs and Erosion Control Blankets (ECBs). Rigorous flume testing at Colorado State University (CSU) with varying shear stresses and flow rates substantiated resistance of high shear stresses up to 15.9 lbf/ft2 (77.6 kgf/m2).

Vegetated GEOWEB TRM System Compared to Rip Rap

The GEOWEB TRM System offers advantages over rip rap for vegetated channels:

  • Streamlined Transition with Boundaries: Smooth integration with boundaries reduces undermining and erosion at boundary points
  • Higher Permeability: Ideal for environmentally low-impact design
  • Easier Integration in Landscape Plan: Less obtrusive and can be incorporated as a “soft” solution (i.e., grassed conveyances) with capabilities of some hard-armored systems

Sustainable Solution for Vegetated Conveyances

Sustainable vegetation in channels can be achieved with the GEOWEB TRM system. Applications that benefit include roadside ditches, stormwater channels, shoreline embankments, dams, spillways, and pond overflow systems. The GEOWEB/TRM system is a more sustainable—and environmentally friendly solution than rip rap for these common applications.

 

 

 

Presto offers full design and specification tools and a free project evaluation service to determine applicability.

Meet the Presto Geosystems Team: Get to Know JP

meet JP imageWe have a great team here at Presto Geosystems, so we thought it would be fun to share a bit more about each member through a new blog series. For our inaugural Meet the Presto Geosystems Team blog post, we are thrilled to introduce José Pablo George—Presto Geosystem’s International Business Manager (BDM).

Let’s get to know JP…

JP

How long have you been with Presto Geosystems?

Time slides and blurs in a funny way. It seems so natural for me to be doing what I do with GEO, as if I’ve always been here and can draw deeply on decades of experiences, yet at the same time I still have the positive outlook and optimism of a freshly minted graduate. The year-over-year calendar and the bits of chrome in my hair suggest a compromise: this year marks my eighth year with GEO; call me a well-seasoned new-ish guy.

Can you tell us a bit about your background?

My specialty is in establishing, culturing, and maintaining business relationships, especially with our international clients. My former life and experiences pre-Presto support this well.

I was a Spanish teacher (secondary schools and technical colleges) for 17 years, and have the linguistic skills and cross-cultural skills thanks to that, as well as the “educating adults” part needed for onboarding new network agents for us. Presto initially hired me as a LATAM BDM, and I gradually took over most of the international world from there!

I´ve developed my chops with quality assurance and network training through the State of WI DOT, technical colleges, and Harley-Davidson corporate in their Quality Assurance programs and motorcycle training programs. I´ve studied Verbal Judo, am a legit Black Belt in Tae Kwon Do, and have negotiated labor-management bargaining contracts from both sides of the table. I don´t shy away from tough conversations, and although I´m usually the “quiet one,” my words have strength and I usually deliver them in a way to make them count.

Additional life experiences of growing up with my artist grandfather, working the family dairy farm, building houses from blueprints, solo motorcycle trips across the country, living and working abroad, and working the world´s most famous pottery kilns have all expanded my perspective, and make for interesting stories to share (another time).

What attracted you to the world of geosynthetics?

Initially it was softball and Spanish that attracted me to the world of geosynthetics. The former Geosystems Director and I played on a rec league softball team, and he kept trying to hire me for my Spanish skills. When two other Fortune 500 companies offered me positions (also due to my Spanish skills), I figured a career change merited a closer look. I decided to leave teaching for the corporate world, and am glad to have made the leap. Since starting with Presto, I have obtained my CPESC certification and have learned so much more about geosynthetics and engineered soil stabilization solutions. I´m even published and on patents now!

What does your job entail? Can you take us through a day in the life as an International Man of Myst…umm, I mean International Business Manager?

The day of an International Manager is always a mystery… yet also contains some comfortable stability. Every single day I am talking with contacts from around the globe. My mobile number is my WhatsApp, Viber, Signal, Teams, text, and Messenger number… and I use each of them to reach our agents and clients in the way that is most natural to them. Every day I get to use my Spanish language skills, and I have also learned a bit of Dutch, Setswana, Japanese, Portuguese, French, and German. Most days I am offering design and sales support, sourcing appropriate supporting resources for projects, and doing my part to keep our solutions present in the minds of engineers and clients. Most weeks I am presenting the details of one of our solution sets for a particular application, such as Infrastructure Resilience for Roads and Bridges, Channel Armoring, or Mine Slope Reclamation… sometimes in English, sometimes in Spanish.  Sometimes it means presentations… of whitepapers… to government entities… to International Erosion Control or Geosynthetics groups, and the like. Once upon a time, my job meant lots of travel to meet with clients IRL, not just virtually. I look forward to the travel again someday. Really, my job entails building relationships with the right connections. Sometimes I have to seek them out, sometimes connections find us. Either way, I must develop them into something.

What do you like most about your job and/or what do you like most about this industry?

What I like most about my job is the connection to people and places around the globe. The industry allows me to offer lasting, valuable solutions to real problems. We solve the most challenging soil stabilization problems, and give the world a strong foundation to build on. There is a bit of superhero stuff in that! What´s not to like?

Can you tell us a little about what it’s like working with international business partners?

Ha! Never before have I understood time zone differences and ultra-long project gestation times so well.  I organize my day to speak with different parts of the world at different times… Europe and the UK at the start of my day, LATAM and SADC throughout the day, Asia Pacific and MENA towards the end of the day… it is a lovely variety! Not always so clean cut, but that generalizes it some. I must exercise great patience… as anything international involves extra touches and tending. With all of our international projects and partners, it comes back to building and keeping strong relationships, as well as ease of use, reliability, and high performance. Our partners know we will do what it takes, and with integrity, to help them find success.

What do you enjoy doing when you aren’t out helping solve the world’s soil-stabilization and erosion challenges?

I love spending time in the forest, and am fortunate to live in a region that allows me to experience the changing seasons with unhindered access to the woods. My family and I love to camp, hunt, fish, ski, bike, hike, and enjoy time together outdoors. I hate ticks and mosquitoes, and most other things that try to bite me without my permission… but generally speaking will spend as much time as possible in the woods.

What is your favorite place in the world to visit?

There are so very many places I have yet to see!!! How can I pick just one?!

Tops on my list of having been: Cartagena, Colombia; Granada, Nicaragua; La Rioja, Spain; the Frankfurt area of Germany; and the Parque Manuel Antonio in Costa Rica.

Soon-to-be favorites include Paris and the wine country of France, and the Amsterdam area of the Netherlands.

An eventual favorite trip will be a summer camping trip to the Denali area of Alaska… and to Banff, Alberta, Canada. Maybe back to the Patagonia area of Argentina, this time to fish and not just for work… and to other parts of Japan beyond the Tokyo area, including Sapporo, Osaka, and Fukuoka.  So many adventures yet to be had!

If you could meet anyone, living or dead, who would you meet?

This is a tough one. At this juncture in time, if I had to pick just one person I´d like to meet, I would ask Keanu Reeves to accompany me for a long walk and talk at a dog park with our pets. He is also an International Man of Mystery, a “cool breeze over the mountains” that is aware of his celebrity status yet is generous and careful with his presence. I admire the way he sticks to his principles and manages to stay cool and look at the bright side, with kindness, humility, and gratitude. He models being a good human in a way the world needs right now. If Keanu turned me down, I would ask Steve Martin to share his mad banjo skills and a few jokes with my son, or Shakira to sing with my daughter.

What would you name the autobiography of your life?

The Next Adventure Awaits…

JP Book

GEOWEB® Geocell Reinforcement Improves Structural Performance of Railway Track Beds

Every year, railroads dedicate a great deal of capital and resources toward creating and maintaining high-quality track profiles. Providing a well-designed track profile is the foundation on which a successful rail line operates. With ballooning rail traffic carrying heavier loads than ever and increased occurrence of extreme weather events, a stable track profile is essential for successful operation.

GEOWEB® geocells have been used in the track bed for rail applications worldwide for more than 40 years. Through an interconnected honeycomb-like network, the HDPE-based GEOWEB Soil Stabilization System provides apparent cohesion and strength to materials that would otherwise be unstable over soft subgrades. Geocells stabilize the ballast, reduce vertical and lateral stresses, and limit ballast movement. Stabilization within the geocell system provides a longer lasting track profile that extends rail service life, while also reducing maintenance cycles and recurring maintenance costs. Research has shown that geocells reduce settlement of the ballast foundation and can reduce required cross-section thicknesses by up to 50%. This is particularly advantageous where track beds must be constructed over soft soils. The reduction in thickness leads to cost savings, along with an accompanying reduction in carbon emissions due to decreases in aggregate processing, transportation, handling, and installation. In general, geosynthetics offer tremendous potential in reducing carbon emissions from civil construction projects, in many cases by 50% or greater.

North West Electrification Programme Case Study

In the United Kingdom, Network Rail encountered extremely soft soils with low shear strengths during track modifications to the North West Electrification Programme. Due to soft subgrade conditions, conventional track design methods resulted in cross-sections as thick as 1 meter. Poor soil conditions along the track route required a soil stabilization solution to improve undertrack stiffness and provide a more cost-effective solution. The Network Rail Track Bed Investigation (TBI) team elected to evaluate an alternative solution using geocells to reduce required cross-section thicknesses. The GEOWEB Soil Stabilization System has been used under track in the United Kingdom since the 1980s; however, very limited information was collected at that time to document the resulting improvement in performance. Therefore, the TBI team used in-house numerical modelling to validate the design approach, and results indicated that a geocell-stabilized track performed as well as the conventional full-thickness cross-section. Based on this information, combined with the demonstrated long term stabilization of the above-referenced early installations, the TBI team elected to use the alternate track bed design incorporating GEOWEB Geocells. The North West Electrification Programme subsequently approved the use of geocells on a number of sections with the goal of reducing construction depth, in turn, reducing costs associated with track enhancement and long term maintenance.

After installing the GEOWEB Soil Stabilization System on the North West Electrification Programme in 2017, track quality improved significantly. The reduction in the required track bed construction (40% reduction in granular fill material), reduced the cost of track enhancement by approximately 22% (Wehbi, et al., 2018). Network Rail also realized the benefit in the ability to use granular fill or course sand as ideal infill materials. Network Rail’s experience using geocells has shown substantial construction cost savings and benefits to the structural integrity of the track bed (Wehbi, et al., 2018). Network Rail has also monitored Willesden North on the London North East and Newham Bog on the London North West in addition to the Northern West Electrification Programme, which show similar results and benefits.

Based on their success using the GEOWEB system in track bed applications, Network Rail developed a guide providing a summary of the benefits from research and testing, design recommendations, and best practices. In August 2020, Network Rail issued, “The Use of Geocells in the UK Railway Track Bed, Technical Guide.” The guide provides technical guidance based on extensive research conducted at the University of Kansas (UK) and Oregon State University (OSU), which includes existing geocell design methods, case studies from successful installations, and industry-proven installation methods utilizing specialized geocell ATRA® connection keys. The guide served as a reference for development of the Network Rail Track Bed Standard NR/L2/TRK/4239, Issue 2, issued September 2020, which contains detailed design information and guidelines for using geocells in track bed applications.

Network Rail has approved the GEOWEB® Soil Stabilization System as the solution in areas with soft soils to improve and regulate track bed stiffness, while reducing maintenance, installation time, and cost. GEOWEB® geocells achieve all requirements of the Network Rail Track Bed Standard NR/L2/TRK/4239, Issue 2 and accompanying guide “Use of Geocells” for below track installations.

Protecting Environmental Geomembrane Covers With Suspended GEOWEB Geocells

Economic pressure, the desire for green solutions, and the intensification of climate extremes have converged to create a need for better methods to effect soil stabilization. Fortunately, a proven technology exists that addresses issues associated with these conditions and provides a more stable cover solution for landfill covers, lagoons, stormwater containment basins, and other geomembrane-covered systems. Soil, aggregate, and concrete protective covers over geomembranes can be secured against known gravitational, hydrodynamic, and seismic forces using the GEOWEB® Soil Confinement System.

Soil and aggregate are commonly used as a protective cover over liners on slopes of 3H:1V or less. However, when slope gradients are greater, unconfined soil and aggregate covers are typically unstable and not used. In arid areas, cover depth may range from 75 mm (3 in) to 150 mm (6 in). Where conditions support vegetation, cover depth may range from 100 (4) to 600 mm (24 in) or greater where the final depth is a function of the characteristics of the desired vegetation. Regardless of cover depth, if an extreme rainfall event occurs that is 10%, or greater than what would typically be expected, soil mass increases, assumed friction angles decrease, and factors of safety for soil stability drop to a point where failure of the cover occurs and exposure of and/or damage to the geomembrane results.

Suspended GEOWEB Solution
The use of the GEOWEB 3D slope cover system best addresses critical details when designing or remediating geomembrane covers. With the aging infrastructure of dams, impoundments, and landfills, design engineers are looking for innovative and cost-effective solutions to build and repair new and existing facilities. The adaptability of the 3D system provides geomembrane protection while contributing to an easier and faster installation process.

Structural Support System
Because traditional stake anchoring would puncture the geomembrane, the GEOWEB system is suspended from the crest of the slope through an integrated structure of tendons and load transfer clips. This structural support system directly protects the geomembrane from accidental puncturing and natural degradation–which indirectly prevents soil contamination and erosion. The structural support also allows the GEOWEB system to work on slopes that are much greater than 3H:1V.

A variety of infills may be used, tailored to a project’s specific needs. When lining a landfill cover, crushed aggregate or vegetated infills are common because they put less pressure on the geomembrane cover and allow for growth of the landfill if necessary. For more structural projects, such as dam linings, concrete infill may be the better choice and may allow a thinner concrete cross-section for a reduced cost. This demonstrates another unique aspect of the geocell system, in that the 3D structure of the geocell can act as the formwork for a concrete pour, eliminating the need for expensive and timely construction techniques. Full design evaluations should be performed in order to analyze the loading, shear forces, and factors of safety on each project.

 


Read Technical Paper >>

Original paper entitled, “Failure of a Landfill Cover and Remediation using Geocells” was presented at the First Pan American Geosynthetics Conference & Exhibition, March 2008, Cancun, Mexico. Original paper was co-authored by Mauricio Abramento, PhD, CEG Engenharia, Marcos Mello Rocha Campos, MSc, GEOKLOCK Consulting and Environmental Engineering, Claudia Vasquez Bastias, Fiberweb Bidim and Daniel Senf, PE, CPESC, Presto Geosystems.

GEOBLOCK Grass Pavers: Fire Lane Access System

GEOBLOCK® POROUS PAVEMENT SYSTEM

Environmental regulations that control and limit stormwater runoff, reduce impervious surfaces, and increase green space have resulted in the growth of permeable pavements for traffic areas. The GEOBLOCK Porous Pavement System offers support for all vehicular loadings and protects the grass from the  damaging effects of traffic while allowing natural groundwater replenishment.

Examples of the GEOBLOCK system providing solutions for fire access lane requirements are illustrated in this case study summaries below.

Test 1: The City of Kentwood (1994)

Kentwood, Michigan

GEOBLOCK System Put to the Test

The City of Kentwood, Michigan put the GEOBLOCK system through a worst-case scenario field test to measure performance and prove the system’s capabilities.

Prior to testing, a series of less-than-ideal installation conditions were established:

  • Five inches of sand subbase was installed, developing a base support capacity of only 2.8% CBR.
  • GEOBLOCK units were laid parallel (rather than perpendicular) to the direction of traffic.
  • Edge restraints, typically used to help prevent block shifting until vegetation, were omitted—both of which help anchor the system.
  • The test area was not proof-rolled prior to load applications.

The fire marshal directed a 60,000 lb (22,400 kg) ladder/pumper to drive onto the unfilled 13 ft x 48 ft (3.9 m x 14.6 m) GEOBLOCK test pad, drop its outriggers and begin tests while geotechnical engineers monitored the systems performance.

After a series of rigorous tests, the ladder/pumper stayed on the GEOBLOCK pavement for a full hour.

The Results:

Under loading, inspection revealed only a 1/2 in (13 mm) deflection in the pavement system. After removal of the load, the GEOBLOCK pavement rebounded to its original condition in less than one hour, and the units were recovered for future use. As a result of this test and the system’s performance, the City of Kentwood approved the GEOBLOCK Grass Pavement System for use on its fire access lanes.

Case Study 1: Microsoft Campus (1996)

Redmond, Washington

The Challenge

As Microsoft Corporation’s facilities expanded through the years, so did their need for fire access lanes at their campus buildings. Grassed access lanes rather than hard-surface paving were desired to enhance the aesthetics of the new building and grounds. The search for a reliable porous pavement system led them to the GEOBLOCK Grass Pavers.

The Solutions

At their Washington State Campus, 8,600 square feet of the GEOBLOCK system was installed for permeable, grass fire access lanes around nine campus buildings.

Previously, 9,000-square-foot installations were installed around three other campus buildings. At other locations, existing fire access lanes were expanded using the GEOBLOCK system to meet new code requirements.

The Results

Implementation of the GEOBLOCK system helps preserve the campus’ natural look while providing the load support necessary to accommodate all emergency vehicles.

Test 2: AT&T Corporate Center (1994)

Basking Ridge, New Jersey

A worst-case scenario field test was also required by the Lyons Township Fire Department, New Jersey prior to approving the GEOBLOCK System for a fire access lane at the new AT&T corporate convention facility.

A test pad was installed in front of the facility adjacent to a concrete block entrance drive. Side restraints, sometimes used to anchor the pavement system, were purposely omitted. A few weeks later with only light grass established, the Lyons Township Fire Department was ready to begin the testing.

Under full pressure, firemen turned the hose directly on the GEOBLOCK platform and proceeded to saturate the test pad. With water still standing on the pad, an 80,000 lb. fire engine was backed over the saturated area, and with the outriggers lowered, was lifted off its tires. A series of tests were performed under full load and less-than-ideal conditions to determine the capabilities of the GEOBLOCK system.

The Results

After passing the tests successfully, the Fire Department approved the GEOBLOCK system at the AT&T Corporate Center for fire access use.

Case Study 2: Friends University (1999)

Wichita, Kansas

The Challenge

When officials at Friends University planned to beautify the exterior of the campus’ newly renovated Davis Hall, it included removing the large driveway leading up to the building’s main entrance. The university wanted to create a large open area, or pedestrian mall, where campus events could be held in front of the 110-year-old Davis Hall. The new design included a 76-ft diameter paving stone mosaic at the Rose Window Plaza in front of the hall to replicate the pattern of the stained glass window. The finished concept would include sidewalks, flowerbeds, and period lights.

Removing the frontage road and circle drive left the mall with diminished emergency vehicle access. The university sought an alternative to hard surface paving that would blend naturally with the green look of the campus while providing the necessary load support for maintenance and emergency vehicles.

The Solution

The GEOBLOCK Load Support Solution was chosen to best complement the new pedestrian mall and paving stone design work. About 9,000 square feet of the GEOBLOCK system was installed with an engineered base of sand and topsoil. Topsoil and a hearty bluegrass and fescue blend sod were placed in the cells of the GEOBLOCK units.

The Results

The GEOBLOCK system met the University’s need for vehicular and pedestrian load support over grassed areas while complementing the aesthetically pleasing entrance and protecting the grass from the harmful effects of the traffic.

Case Study 3: Homestead Village Complex (1997)

Bellevue, Washington

The Challenge

Faced with the common problem of providing emergency vehicle access while maintaining desirable green space, architects and contractors building the Homestead Village Complex rejected traditional paving materials in favor of a permeable system.

The Solution

The GEOBLOCK System was utilized in three areas at the apartment complex—two fire access lanes and one access road to the complex’s water detention pond. Three areas totaling 3,000 square feet were installed in less than three days, starting from site preparation through seeding.

The Results

After the system was fully vegetated, tests were performed by the local fire department, and the GEOBLOCK system was approved for use.

Case Study 4: Intervet, Inc. (2002)

Desoto, Kansas

The Challenge

The mall area in front of the pharmaceutical company’s office building was designed with a series of intersecting concrete roadways for emergency access. The owner desired green space for visual appeal in the large adjacent areas. However, a typical turf-only surface would not reliably support the load of fire trucks and emergency vehicles.

The Solution

The GEOBLOCK system was chosen for its aesthetic appeal, ease of installation, and load support capabilities. The GEOBLOCK units were placed on a prepared base such that their tops were flush with the adjacent concrete roadways. Units were set in place, cut as needed to conform to site irregularities, infilled with topsoil, and seeded.

The Results

The landscape contractor and owner were very satisfied with the final solution. When tested under full load, less than one-half inch of deflection was noted in the loaded areas.

GEOWEB Geocells Combined with a Turf Reinforcement Mat (TRM)

GEOWEB® System – Research Synopsis

Research Objective
Measure the performance of the GEOWEB (GW) material combined with a turf reinforcement mat (TRM) (integrated system) with topsoil infill and vegetation under varying shear stresses and flow rates to quantify both hydraulic forces and
corresponding soil loss.

The test consisted of a series of continuous one-hour flows over the GW-TRM system at incrementally increasing discharges. The performance threshold was defined as the point at which 0.5 inches (13 mm) of soil loss occurred.

Research Scenario

The Research Facility
Steep-Gradient Overtopping Facility (SGOF) at the Hydraulics Laboratory of the Engineering Research Center (ERCD) at Colorado State University (CSU), Ft. Collins, Colorado

Test Timeframe
April 2005-August 2006

Test Materials

  • GEOWEB Soil Stabilization System
  • North American Green C350 Turf Reinforcement Mat

Scope of Test

Hydraulic performance testing was conducted on an integrated system comprising the GW30V textured/perforated GEOWEB System and the North American Green C350 composite turf reinforcement mat. The C350 TRM was chosen for its known performance in the test apparatus. Six tests were conducted under the research program to measure the performance of the integrated system, identify stability threshold conditions, and quantify both hydraulic forces and soil loss.

Assembling the Test Components

  • The selected textured/perforated GEOWEB section was placed in the test apparatus and topsoil infill added.
  • When the GEOWEB cells were completely infilled with topsoil, the soil was lightly tamped.
  • Grass seed and mulch were added to finalize the growing medium.
  • The turf reinforcement mat was secured over the textured/perforated GEOWEB section by ground staples at defined intervals in conformance with the manufacturer’s recommendations.
  • Vegetation was established over a 14-week period to allow root system integration within the perforated cells of the GEOWEB material. Kentucky bluegrass was the chosen vegetation for this series of tests.

Test Procedures/Result

The test apparatus is lifted and positioned in place in the flume with a 2h:1v slope. In an effort to model storm conditions, the soil was saturated prior to the six tests. The integrated system was subjected to flow discharges ranging from 10 ft/sec (3.0 m/sec) to 27 ft/sec (8.2 m/sec). Two sets of water surface elevation data were taken; one at the beginning and one at the end of each hour-long flow to obtain an average depth. Vegetation density counts were also measured prior to and directly after each test at upstream, midstream, and downstream locations.

Observations

Exposed to the extreme flows, and despite ordinary topsoil infill and typical TRM staple patterns, the system showed no measurable soil loss. It was observed that the vegetation had decreased stem and blade count during the total testing timeframe, however at a decreasing rate of loss for each incremental test.

Chosen vegetation type will influence the stem and blade loss. Typically a hardier grass type or blend would be used for field applications rather than pure Kentucky bluegrass. At the completion of the test, an extracted soil sample showed vegetative root penetration to a depth of 1.5 inches (38 mm), with larger roots interacting with the cell wall perforations. As future growth occurs, root interaction will increase.

Testing Summary/Conclusions

No system instability was observed for shear stresses up to 15.9 lbf/ft2 (77.6 kgf/m2) and for average velocities up to 26.5 ft/sec (8.1 m/sec) with peak velocities over 29 ft/sec (8.8 m/sec). Due to facility constraints that prevented testing higher velocities than those reported, system failure limits were never found. The test results for the integrated system far exceed the limits of separately reported values of the GEOWEB Cellular Confinement System (CSS) and turf reinforcement mats with topsoil/vegetated soil.

Field Applicability

The results of this integrated system testing can be applied to highway drainage ditches, spillways, dam, and pond overflow systems and other vegetated channels exposed to high shear forces and intermittent, longer-duration velocities. This system replaces rip rap with a less expensive, low maintenance, aesthetically pleasing green solution.

Exclusivity of Results

The results of the testing are exclusive to the materials utilized in this test. Specifically, no inference shall be drawn from this research review indicating suitability of any cellular confinement system other than the genuine GEOWEB Cellular Confinement System. Due to the challenging nature of the projects for which this application applies, we strictly warn the reader of the potential for significant infill loss, project failure, and/or loss of property or life if substitutions are made including, but not limited to the GEOWEB Cellular Confinement product and a properly prepared engineering design analysis.

Certifiable Results

Results of this testing/research are certifiable and only available through Presto Geosystems.

Download CSU Vegetated Research Summary >>

Solar Installations on Closed Landfills: Using Geosynthetics to Overcome Redevelopment Challenges

Written by: Michael Dickey, P.E. (WI, FL, GA, NC), Director

Redevelopment of closed landfills and capped solid waste sites represent a unique opportunity for landfill owners, solar developers, and communities to work together to put underutilized properties back into productive use. Moreover, many such sites are conveniently located near existing transmission infrastructure and may be easier and more economical from an interconnection standpoint than rural greenfield sites.

However, building over a closed landfill poses unique challenges because most landfills are covered by an engineered cap not typically designed to support loads from permanent foundations or heavy equipment. Additionally, state and federal regulations generally prohibit any activity that could potentially breach or damage the cap. Therefore, retrofitting a closed landfill for utility-scale or community solar projects requires careful planning. Ultimately, the project must not jeopardize the intent of the original cap design; that is, to protect human health and the environment.

closed landfill with vegetation

Selecting a Suitable Foundation

Concrete slabs and pre-cast ballast footings are both foundation options for solar system installations on landfill caps. In general, concrete slab foundations are heavier than ballast footings and pose a higher risk of creating landfill settlement and side-slope stability issues. Ballasted footings are a lighter-weight option and may be suitable for flat landfill surfaces; however, engineering difficulties emerge as the slope of the landfill surface increases. Ultimately, the foundation must be designed to protect the system against wind uplift and sliding without exceeding the allowable bearing capacity of the cap.

Allowable bearing capacity is very site-specific and is typically a function of cap thickness and composition, combined with appropriate considerations to account for the makeup and age of the underlying waste material. For example, old construction debris that has been previously compacted will not experience significant settlement because of low biochemical degradation; therefore, the likelihood for damage to the cap, or the solar installation, can be expected to be relatively low. Conversely, a thin cap over a relatively new landfill cell containing unconsolidated municipal waste, which would see short- and long-term settlement, may be at a much higher risk of damage, and any new construction may therefore be subject to a much lower allowable bearing capacity requirement.

There are methods to improve bearing capacity and mitigate settlement for new developments on previously closed landfills. Geosynthetics can be employed to dissipate loads from foundations and construction equipment and provide long-term protection against the damaging effects of differential settlement. Geocells, in particular, can be integrated into the leveling course beneath ballast footings, or the base layer beneath a concrete slab, to improve the allowable bearing capacity and protect solar foundations from cracking and settlement problems.

Improve Allowable Bearing Capacity, Protect Against Differential Settlement Using Geocells

Geocells—recognizable by their unique three-dimensional honeycomb-shaped appearance—are a specialized geosynthetic material widely used in construction for load support, slope/channel protection, erosion control, and mechanically stabilized earth (MSE) walls. Compared to planar geosynthetic products such as geogrids—which commonly rely on expensive imported high-quality aggregate—geocells are highly versatile and can be filled with a variety of commonly available and economical infill materials. Compatible infill materials include sand, soil, aggregate, concrete, pulverized debris, recycled asphalt, or other locally sourced materials.

geoweb loadWith geocells, it is not uncommon to see an overall reduction in the required thickness of the base layer or leveling course in a load support application by 50% or more, along with an overall improvement in allowable bearing capacity. This applies to foundations as well as permanent or temporary site features, such as access roads or construction platforms.

In load support applications, when a static or dynamic load is applied to a geocell-reinforced layer, lateral earth pressures are mobilized and transferred across a three-dimensional network of interconnected cells. The layer essentially performs like a composite material, facilitating a phenomenon known as the mattress effect. As a result, applied loads are more widely spread, resulting in a uniform distribution of applied stresses, as well as a reduction in the magnitude of these stresses to underlying layers. This results in an effective increase in the allowable bearing capacity and a reduction in differential settlement.

Moreover, in many cases, geocells allow for the beneficial reuse of on-site materials, eliminating the need to purchase expensive aggregate or imported structural fill. These advantages not only offer the potential for savings in overall construction costs, but they also contribute to a significant reduction in carbon emissions due to less aggregate/fill processing, transportation, and handling.

GEOWEB® Geocells: A Versatile Site Development Solution for Solar Projects

The GEOWEB Geocells have been used for load support and foundation applications worldwide for more than 40 years. Developed in collaboration with the U.S. Army Corps of Engineers in the late 1970s, Presto co-invented the technology known today as geocells. Since that time, Presto has endeavored to improve and innovate geocell technology, creating what is known around the world today as the GEOWEB® Soil Stabilization System. GEOWEB Geocells are made of 100% high-density virgin polyethylene and do not contain any recycled material, fillers, or exotic polymer, all of which can negatively affect performance. Complete with a full line of accessories for ease of installation and long-term performance, the GEOWEB Soil Stabilization System is the most advanced geocell technology in the industry.

photo of solar panels on solar farm with blue sky and clouds background

The GEOWEB system has been used on every continent and on thousands of load support, slope stabilization, channel protection, and retaining wall projects. Based on accredited third-party laboratory analysis using internationally recognized test methods, The GEOWEB geocells are predicted to be durable for a minimum of 50 years and are extremely resistant to long-term weathering and UV degradation. This makes the GEOWEB Geocells an ideal site solution for solar projects that must withstand the long-term effects of climate change and extreme weather events.

Design Support & Resources for the GEOWEB System Applications

The engineering team at Presto Geosystems works closely with engineers and project planners, offering free project evaluation services and on-site support. Our recommendations will deliver a technically sound, cost-effective solution based on four decades of accredited research and testing data. Please contact our knowledgeable staff and network of qualified distributors and representatives to discuss your project needs today.

Related Articles and Case Studies

How GEOWEB geocells were used to combat severe erosion at the Spotsylvania Solar Farm

The History of Geocells

Geocell technology has come a long way over the past four decades. In its early days of development, the geocellular soil confinement system consisted of wax-coated craft paper; a plastic drainage pipe matrix fastened with staples; paper-thin, hexagon-shaped, glued aluminum; low- and medium-density recycled materials; pure polyethylene without UV stabilization; and square cells similar to old-fashioned egg carton separators.

The Invention of Modern Geocell Technology

In the late 1970s, the U.S. Army Corps of Engineers (USACE) contacted Presto Products Company—a private-label consumer packaging manufacturer—to develop a more robust honeycomb-shaped confinement system that would maintain load-bearing strength under heavy vehicle loads.

Working with Steve Webster at the Waterways Experiment Station (WES), Presto’s Gary Bach devised a method to weld polyethylene strips to form a cellular structure. This innovative system became known as Sandgrid and was used by the military primarily for road applications.

After the development of Sandgrid, Presto Products created a new business unit to focus solely on the geosynthetics business. With this expansion, Presto Geosystems® was established.

Presto Geosystems and the USACE tested various resin blends and concluded that virgin high-density polyethylene (HDPE) provided superior weld consistency and structural strength. Presto Geosystems introduced the GEOWEB® Cellular Confinement System (CCS) to the geosynthetics market in the early 1980s.

In the years following the initial testing, the geocell technology continued to advance, paving the way for the use of geocells in new civil and military applications. In addition to a load-support solution, the GEOWEB system provided soil stabilization for the rapid construction of fortified walls in the United States’ Middle Eastern combat zones, starting with Operation Desert Storm in the early 1990s.

The GEOWEB System’s Big-Screen Debut

The GEOWEB system made its Hollywood debut in the 1994 sci-fi action-adventure movie, Stargate. To serve as the desert landscape in the film, filmmakers chose the barren setting surrounding Yuma, Arizona. However, very loose sands at the film location made transportation around the site virtually impossible. Crews used the GEOWEB system to create an “instant road,” using on-site sand as the infill, that allowed vehicles and heavy equipment to move around the desert with no rutting or loss of traction.

Director Roland Emmerich stated, “We never would have been able to move around the desert without [GEOWEB].”

Fast-Forward to Today’s GEOWEB Geocells

The GEOWEB system did not let fame go to its head, but these early applications and projects did help cement its stardom in the world of geosynthetics. Since its introduction in the 1980s, the GEOWEB Soil Stabilization System has been used on every continent and on thousands of load support, slope stabilization, channel protection, and retaining wall projects.

Presto Geosystems is a leader in the stormwater and site development industry with eco-friendly, custom-tailored solutions to meet the most demanding soil and water problems. We have been manufacturing high-quality, innovative products for over forty years. Our proven solutions are designed to handle unique challenges, lower project costs, and reduce construction time with minimal environmental impact. Our products are backed by accredited research, internationally recognized testing, and quality processes, ensuring high-performing and long-lasting solutions.

We are committed to the complete project cycle. We invest with partner engineers, contractors, and owners to solve their site challenges. Our value starts with design assistance, and we stay with you through project completion.

Our Mission is to Give the World a Strong Foundation to Build On.

With the commercialization of geocell soil confinement technology in the early 1980s, Presto Geosystems made history as one of the early pioneers in the world of geosynthetics. Four decades later, that innovative spirit is as alive today as it was at the beginning of our journey. Our products have been used on every continent and on thousands of projects to improve infrastructure reliability and environmental quality for communities around the world. We believe in the human spirit of innovation, and we believe that reliable infrastructure and environmental quality are foundational to the prosperity and well-being of the world’s communities.

Design Support & Resources for GEOWEB Applications

The engineering team at Presto Geosystems works closely with civil engineers, offering free project evaluation services and on-site support. Our recommendations will deliver a structurally sound, cost-effective solution based on four decades of accredited research and testing data.

Download The History of Geocells Article >>

Advancing the Mining Industry’s Transition to Sustainable Practices with Geosynthetics

Written by: Michael Dickey, P.E. (WI, FL, GA, NC)

Mined materials are essential to our everyday lives. We use these valuable minerals in nearly every sector of the economy—they are necessary to construct roads and buildings, manufacture vehicles, build computers, and generate electricity. Additionally, the mining industry stimulates economic growth by providing employment opportunities and generating tax revenue that helps fund vital public services, such as hospitals and schools.

As the mining industry navigates environmental, social, and governance (ESG) issues, there is a sense of urgency to adopt sustainable or “green” mining practices. Green mining can be defined as technologies, best practices, and mine processes that are implemented to reduce the environmental impacts associated with the extraction and processing of metals and minerals.

The Mining Industry Faces Unique Challenges

When it comes to sustainable development, operation, and closure of mines, the industry faces myriad challenges—not the least of which are poor soil conditions, weak subgrades, and other geotechnical challenges that can complicate miners’ efforts to meet ESG goals.

In this regard, some of the more common geotechnical challenges that mine operators must contend with include:

  • Constructing and maintaining heavy-duty haul roads.
  • Stabilizing and protecting slopes.
  • Tailings management and site reclamation.

Compared to conventional methods, integrating geosynthetics into designs can help achieve a more sustainable approach to overcome many of these types of geotechnical challenges.

Heavy-Duty Haul Roads

Haul roads are an integral asset to a mining operation, in the same manner as trucks and shovels. They are a critical component of mining infrastructure, and they directly influence the operational efficiencies of mine sites. Haul truck payload capacities range from 36 tons up to a staggering 450 tons (for ultra-class trucks), so these roads require special design considerations to withstand heavy and continuous traffic. However, extreme weather conditions and soft subgrades present challenges to both the construction and long-term performance of heavy-duty haul roads.

At a gold mine in Latin America, owners adopted a value engineering approach to optimize haul road design and minimize long-term costs associated with recurring maintenance and repair. They accomplished this by using the GEOWEB® Cellular Confinement System to stabilize and confine road-base materials. The geocell system allowed for the beneficial use of abundantly available coarse river sand for the placement of base materials.

GEOWEB mining haul road

Due to the improved bearing capacity of the system, there was also a substantial reduction in overall section thickness requirements. This resulted in construction savings of over $150,000 per kilometer. Additionally, because of improved road stability, mine operations saw a 65% reduction in maintenance costs as fewer grader passes were needed and requirements for frequent replacement of wear course materials were substantially reduced.

Slope Protection

In addition to haul-road applications, geocells can be used on slopes to resist sliding, prevent severe erosion from surface runoff, and facilitate the construction of steep slopes.

The New Caledonia mine in the South Pacific—one of the largest nickel mining sites in the world—faced the formidable challenge of protecting the mine slopes from erosion due to highly erodible soils, mountainous terrain, and extreme weather (cyclones).

The owner ultimately selected a slope protection strategy consisting of the GEOWEB geocells infilled with waste aggregate. The GEOWEB Slope Protection System was designed to perform as a robust protective veneer over the existing terrain. The beneficial reuse of readily available onsite materials meant direct cost-savings to the owner compared to previous, less successful methods.

geoweb mining slope

Tailings Management and Site Reclamation

Tailings are waste products that result from mining, crushing, grinding, and chemically treating ore. Tailings storage facilities typically contain crushed rock, water, and chemicals, and are designed to prevent the uncontrolled release of material into the environment during operation and closure. These facilities are often set up as settling ponds that are later capped in place during site reclamation activities.

At the Moon Creek abandoned mine site in Idaho, for example, reclamation efforts included the construction of a tailings repository for onsite disposal of approximately 88,000 cubic yards of flotation tailings, contaminated soils, and waste rock. Project objectives were to reduce the release of heavy metals to Moon Creek, rehabilitate the site to limit human health and ecological exposures, and improve trout habitat.

The tailings repository was built on a special foundation, allowing its construction over soft, saturated in-situ tailings. Foundation elements included an impervious below-grade scour-protection berm, gravel and limestone wick drains, and a GEOWEB mattress filled with waste rock to provide a surcharge over the tailings and lateral load reinforcement.

Following the placement of waste materials, the repository was covered with an engineered cap composed of a geosynthetic clay liner, overlain by a gravel drainage layer and two feet of soil. Lastly, an erosion protection mat was installed over the surface of the cap to provide root matrix reinforcement for the native grasses used in the seed mixture.

geoweb mattress

Design Support & Resources for Mining Applications

The engineering team at Presto Geosystems works closely with civil engineers, offering free project evaluation services and on-site support for mining haul roads, slope protection, basin containment, channel armoring, and tailings protection.